A stakeholder requests a change that will significantly improve user experience but will delay the project by two weeks. What should the BA do first?
publish date: 2026/03/11 04:17:12.630873 UTC
volume_mute
Correct Answer
Assess the impact of the change
Explanation
Always assess impact before taking action on a change request.