True or False: The activities in the requirements engineering process are carried out in a strict sequence, one after the other, with no overlap.

Correct Answer

False

Explanation

False. The activities in the requirements process are not simply carried out in a strict sequence. Requirements analysis continues during definition and specification, new requirements come to light throughout the process, and the activities of analysis, definition, and specification are interleaved.

Reference

Software Engineering, Ian Sommerville, 9th edition