True or False: The activities in the requirements engineering process are carried out in a strict sequence, one after the other, with no overlap.
Correct Answer
False
Explanation
False. The activities in the requirements process are not simply carried out in a strict sequence. Requirements analysis continues during definition and specification, new requirements come to light throughout the process, and the activities of analysis, definition, and specification are interleaved.