When conducting a stakeholder analysis, the BA realizes that a key department head has high influence but low interest in the project. How should this stakeholder be managed?
publish date: 2026/03/10 05:24:5.511715 UTC
volume_mute
Correct Answer
Keep satisfied
Explanation
High Power/Low Interest = Keep Satisfied (Power-Interest Grid).