An organization is performing 'Benchmarking'. Its 'Order Cycle Time' is 5 days. The industry leader's time is 2 days. What is the 'Benchmarking Gap' in days?
publish date: 2026/03/09 19:32:37.289617 UTC
volume_mute
Correct Answer
3 days
Explanation
The gap is the absolute difference between the current state performance and the benchmark targete: 5 - 2 = 3.