A project is in the elicitation phase. The BA has identified 40 stakeholders. According to the communication channels formula n(n−1)/2, how many channels exist, and how should this influence the BA's 'Plan Stakeholder Engagement'?
publish date: 2026/03/08 06:39:3.118853 UTC
volume_mute
Correct Answer
780; the BA should use more structured and formal communication methods
Explanation
With 40 stakeholders, the channels are (40 * 39) / 2 = 780. Large numbers of channels require formal governance to prevent information loss.