A BA is performing 'Analyze Potential Value and Recommend Solution'. Solution A has a Net Present Value (NPV) of 120,000 USD and a Benefit-Cost Ratio (BCR) of 1.8. Solution B has an NPV of 140,000 USD and a BCR of 1.4. Which solution should the BA recommend if the goal is absolute value?
publish date: 2026/03/08 05:59:11.445789 UTC
volume_mute
Correct Answer
Solution B
Explanation
NPV measures the absolute total valu ecreated by a project; thereforce, the solution with the highest NPV is preferred for absolute value.