A BA is assessing a solution's efficiency. The 'Value Stream' shows that a process takes 10 hours total. 2 hours are spent on 'Value-Add' activities, 3 hours on 'Business Non-Value-Add' (compliance), and 5 hours are 'Waste'. What is the Process Efficiency?
publish date: 2026/03/08 13:13:4.007730 UTC
volume_mute
Correct Answer
20%
Explanation
Process Efficiency is
\[\frac{\text{Value-add time}}{\text{Total cycle time}} = \frac{2}{10} = 0.20\]