A BA is analyzing a 'Decision Tree'. Branch A has a 60% probability of 50k and 40% of 0. Branch B is a certain 25k. Which branch has the higher Expected Value (EV)?
publish date: 2026/03/09 19:16:58.989144 UTC
volume_mute
Correct Answer
Branch A
Explanation
Branch A: 0.6 * 50,000 = 30,000.
Branch B: 1.0 * 25,000 = 25,000
Branch A is higher by 5,000.