A BA identifies that a proposed design option will take 2 years to implement, but the business need is urgent (needed in 6 months). This design option is failing which check?
publish date: 2026/04/27 21:04:11.681489 UTC
volume_mute
Correct Answer
Schedule Feasibility
Explanation
Schedule feasibility assesses whether the solution can be delivered within the required timeframe to meet the business need.