Stakeholders are in conflict over the priority of two requirements. What is the BEST way for the BA to facilitate a resolution?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Use objective criteria like NPV, risk, and regulatory compliance to re-evaluate priorities.
Explanation
Prioritization should be based on objective business value and risk factors rather than subjective opinions or ease of work.