A BA is assessing the impact of a change and finds it will require a 20% increase in the project budget. Who must the BA consult FIRST?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
The Project Manager
Explanation
Because a budget increase is a project management constraint, the BA must work with the PM to understand if such a change is possible within the project's governance.