During an elicitation session, a BA notices that the stakeholders are using inconsistent terminology for the same process. What should the BA do FIRST?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Document the different terms and create a Glossary.
Explanation
Creating a glossary or data dictionary ensures 'Understandability' and consistency across the enterprise and project stakeholders.