You are presented with a "Value Stream Map" where the "Wait Time" between two steps is 48 hours, but the "Processing Time" is 10 minutes. Where should the BA focus improvement?
publish date: 2026/03/25 11:47:2.563281 UTC
volume_mute
Correct Answer
Reducing the 48-hour wait time (Non-value-add time)