A BA is planning 'Governance' and decides that all changes must be approved by the CEO. What is the likely impact of this decision?
publish date: 2026/04/27 21:14:56.677904 UTC
volume_mute
Correct Answer
Decisions may be delayed due to the CEO's availability.
Explanation
Inappropriate governance (choosing an authority that is too high-level for minor changes) causes bottlenecks and delays.