A BA is monitoring their own performance and discovers that elicitation sessions are taking 50% longer than planned. What should they do?
publish date: 2026/04/27 21:14:55.035594 UTC
volume_mute
Correct Answer
Analyze the cause and identify a corrective action (e.g., better preparation).
Explanation
Performance monitoring requires identifying variances and taking proactive steps to improve the BA process.