A BA has completed elicitation and is now organizing the requirements into a consistent format. They notice that some requirements are missing specific details needed for development to begin. Which task is the BA performing?
publish date: 2026/03/05 03:29:34.064852 UTC
volume_mute
Correct Answer
Verify Requirements
Explanation
Verification ensures that requirements are well-modeled, complete, and meet the necessary quality standards.